>[!Properties]- Page Details > March 28, 2025 > > #Construction/Schedule #Construction/Sub-Coordination #Construction/Smart-PM Brad discussed getting the hit rate from [[Smart PM]] software. He drew our attention specifically to the Window Start Accuracy and Window Finish Accuracy graphs. ![[Window Finish Accuracy—Smart PM Software.png]] If you click on the red part of the stacked bar graph it will drill down to in the case of 03/24/25 the one activity that didn't finish last week that should have. We also talked about exporting that to Excel and then adding three columns: Responsible Party, Roadblocks, and Solution. Filling that out during the sub meeting and using that to ensure were maximizing hit rates on both starts and finishes. Example of the 5 activities that didn't start this week that were scheduled to: ![[Hit Rate Tracking Example.png]]